STORMTECH SC-740

REQUIRED MATERIALS AND EQUIPMENT LIST

  • Acceptable fill materials per the Acceptable Fill Materials Section
  • ADS PLUS and non-woven geotextile fabrics
  • StormTech solid end caps, pre-cored and pre-fabricated end caps
  • StormTech chambers, manifolds and fittings

IMPORTANT INFORMATION

IMPORTANT NOTES:
A. This installation guide provides the minimum requirements for proper installation of chambers. Non-adherence to this guide may result in damage to chambers during installation. Replacement of damaged chambers during or after backfilling is costly and very time consuming. It is recommended that all installers are familiar with this guide, and that the contractor inspects the chambers for distortion, damage and joint integrity as work progresses.


B. Use of a dozer to push embedment stone between the rows of chambers may cause damage to chambers and is not an acceptable backfill method. Any chambers damaged by using the “dump and push” method are not covered under the Storm Tech standard warranty.


C. Care should be taken in the handling of chambers and end caps. Avoid dropping, prying or excessive force on chambers during removal from pallet and initial placement.

ADS “Terms and Conditions of Sale” are available on the ADS website, www.ads-pipe.com. Advanced Drainage Systems, the ADS logo, and the green stripe are registered trademarks of Advanced Drainage Systems, Inc. StormTech® and the Isolator® Row are registered trademarks of StormTech, Inc.

Call StormTech at 888.892.2694 for technical and product information or visit www.stormtech.com

REQUIREMENTS FOR SYSTEM INSTALLATION

Excavate bed and prepare subgrade per engineer’s plans.

Place non-woven geotextile over prepared soils and up excavation walls. Install underdrains if required.

Place clean, crushed, angular stone foundation 6” (150 mm) min. Compact to achieve a flat surface.

MANIFOLD, SCOUR FABRIC AND CHAMBER ASSEMBLY

Install manifolds and lay out ADS PLUS fabric at inlet rows [min. 12.5 ft (3.8 m)] at each inlet end cap. Place a continuous piece along entire length of Isolator® PLUS Row(s).

 

Isolator Row PLUS
Place a continuous layer of ADS PLUS fabric between the foundation stone and the Isolator Row PLUS chambers, making sure the fabric lays flat and extends the entire width of the chamber feet. Drape a strip of ADS non-woven geotextile over the row of chambers (not required over DC-780). This is the same type of non-woven geotextile used as a separation layer around the angular stone of the Storm Tech system.

Align the first chamber and end cap of each row with inlet pipes. Contractor may choose to postpone stone placement around end chambers and leave ends of rows open for easy inspection of chambers during the backfill process.

Attaching the End Caps
Lift the end of the chamber a few inches off the ground. With the curved face of the end cap facing outward, place the end cap into the chamber’s end corrugation.

 

Prefabricated End Caps
24” (600 mm) inlets are the maximum size that can fit into a SC-740/DC-780 end cap and must be prefabricated with a 24” (600 mm) pipe stub. SC-310 chambers with a 12” (300 mm) inlet pipe must use a prefabricated end cap with a 12” (300 mm) pipe stub.

Continue installing chambers by overlapping chamber end corrugations. Chamber joints are labeled “Lower Joint – Overlap Here” and “Build this direction – Upper Joint” Be sure that the chamber placement does not exceed the reach of the construction equipment used to place the stone. Maintain minimum 6” (150 mm) spacing between rows

STORMTECH ISOLATOR ROW DETAIL

Figure 1: Inserta Tee Detail

Click/Tap for Fullscreen
Max Diameter of Inserta Tee Height From Base of Chamber (X)
10" (250 mm) 4" (100 mm)
INSERTA TEE FITTINGS AVAILABLE FOR SDR 26, SDR 35, SCH 40 IPS GASKETED & SOLVENT WELD, N-12, HP STORM, C-900 OR DUCTILE IRON
NOTE : PART NUMBERS WILL VARY BASED ON INLET PIPE MATERIALS. CONTACT STORMTECH FOR MORE INFORMATION.
Max Diameter of Inserta Tee 10" (250 mm) Height From Base of Chamber (X) 4" (100 mm)

INSERTA TEE FITTINGS AVAILABLE FOR SDR 26, SDR 35, SCH 40 IPS GASKETED & SOLVENT WELD, N-12, HP STORM, C-900 OR DUCTILE IRON

 

NOTE : PART NUMBERS WILL VARY BASED ON INLET PIPE MATERIALS. CONTACT STORMTECH FOR MORE INFORMATION.

Figure 2: Isolator Row Detail

Click/Tap for Fullscreen

Figure 3: Inspection Port Detail

Click/Tap for Fullscreen

Figure 4: Fill Material Locations

Click/Tap for Fullscreen

INITIAL ANCHORING OF CHAMBERS - EMBEDMENT STONE

Initial embedment shall be spotted along the centerline of the chamber evenly anchoring the lower portion of the chamber. This is best accomplished with a stone conveyor or excavator reaching along the row.

No equipment shall be operated on the bed at this stage of the installation. Excavators must be located off the bed. Dump trucks shall not dump stone directly on to the bed. Dozers or loaders are not allowed on the bed at this time.

BACKFILL OF CHAMBERS – EMBEDMENT STONE

Backfill chambers evenly. Stone column height should never differ by more that 12″ (300 mm) between adjacent chamber rows or between chamber rows and perimeter.

Uneven Backfill – Incorrect

Even Backfill – Correct

Perimeter stone must be brought up evenly with chamber rows. Perimeter must be fully backfilled, with stone extended horizontally to the excavation wall.

Perimeter Not Backfilled – Incorrect

Perimeter Not Backfilled – Incorrect

BACKFILL OF CHAMBERS – EMBEDMENT STONE AND COVER STONE

Continue evenly backfilling between rows and around perimeter until embedment stone reaches tops of chambers. Perimeter stone must extend horizontally to the excavation wall for both straight or sloped sidewalls. Only after chambers have been backfilled to top of chamber and with a minimum 6” (150 mm) of cover stone on top of chambers can small dozers be used over the chambers for backfilling remaining cover stone.

Small dozers and skid loaders may be used to finish grading stone backfill in accordance with ground pressure limits in Acceptable Fill Materials below. They must push material parallel to rows only. Never push perpendicular to rows. Storm Tech recommends that the contractor inspect chambers before placing final backfill. Any chambers damaged by construction shall be removed and replaced.

FINAL BACKFILL OF CHAMBERS – FILL MATERIAL

Install non-woven geotextile over stone. Geotextile must overlap 24” (600 mm) min. where edges meet. Compact each lift of backfill as specified in the site design engineer’s drawings. Roller travel parallel with rows.

ACCEPTABLE FILL MATERIALS

SELECT A MATERIAL SECTION BELOW TO LEARN MORE

PLEASE NOTE:
*. The listed AASHTO designations are for gradations only. The stone must also be clean, crushed, angular. For example, a specification for #4 stone would state: “clean, crushed, angular no. 4 (AASHTO M43) stone”.

 

**. StormTech compaction requirements are met for ‘A’ location materials when placed and compacted in 6” (150 mm) (max) lifts using two full coverages with a vibratory compactor.

 

***. Where infiltration surfaces may be comprised by compaction, for standard installations and standard design load conditions, a flat surface may be achieved by raking or dragging without compaction equipment. For special load designs, contact StormTech for compaction requirements.

1. 36” (900 mm) of stabilized cover materials over the chambers is required for full dump truck travel and dumping.

 

2. During paving operations, dump truck axle loads on 18” (450 mm) of cover may be necessary. Precautions should be taken to avoid rutting of the road base layer, to ensure that compaction requirements have been met, and that a minimum of 18” (450 mm) of cover exists over the chambers. Contact StormTech for additional guidance on allowable axle loads during paving.

 

3. Ground pressure for track dozers is the vehicle operating weight divided by total ground contact area for both tracks. Excavators will exert higher ground pressures based on loaded bucket weight and boom extension.

 

4. Mini-excavators (<8,000lbs/3,628 kg) can be used with at least 12” (300 mm) of stone over the chambers and are limited by the maximum ground pressures in Table 2 based on a full bucket at maximum boom extension.

 

5. Storage of materials such as construction materials, equipment, spoils, etc. should not be located over the StormTech system. The use of equipment over the StormTech system not covered in Table 2 (ex. soil mixing equipment, cranes, etc) is limited. Please contact StormTech for more information.

 

6. Allowable track loads based on vehicle travel only. Excavators shall not operate on chamber beds until the total backfill reaches 3 feet (900 mm) over the entire bed.